Kaleseramik (KLSER), Yerkรถy Yรผzรผncรผ Yฤฑl Mahallesi’nde kurulumu tamamlanan 5 megavat (MWe) kurulu gรผce sahip arazi tipi gรผneล enerjisi santralini (GES) devreye aldฤฑ.
ลirketten KAP’a gรถnderilen bildirime gรถre, 1196 ada 27 ve 31 parsellerde yer alan tesis, toplam 60.628 metrekare alan รผzerinde inลa edildi.
Santral, Tรผrkiye Elektrik Daฤฤฑtฤฑm A.ล. (TEDAล) nezdindeki kabul iลlemlerinin ardฤฑndan faaliyete geรงti.
Yatฤฑrฤฑmla birlikte ลirketin elektrik enerjisi ihtiyacฤฑnฤฑn bir bรถlรผmรผ yenilenebilir enerji kaynaklarฤฑndan karลฤฑlanacak. Bรถylece enerji maliyetlerinin azaltฤฑlarak รถngรถrรผlebilirliฤinin artฤฑrฤฑlmasฤฑ ve operasyonel karbon ayak izinin dรผลรผrรผlmesi hedefleniyor.
| รzel Durum Aรงฤฑklamasฤฑ (Genel) | |
| Yapฤฑlan Aรงฤฑklama Gรผncelleme mi? | Evet (Yes) |
| Yapฤฑlan Aรงฤฑklama Dรผzeltme mi? | Hayฤฑr (No) |
| Konuya ฤฐliลkin Daha รnce Yapฤฑlan Aรงฤฑklamanฤฑn Tarihi | 12.02.2026 |
| Yapฤฑlan Aรงฤฑklama Ertelenmiล Bir Aรงฤฑklama mฤฑ? | Hayฤฑr (No) |
| Bildirim ฤฐรงeriฤi | |
| Aรงฤฑklamalar | |
Yerkรถy Yรผzรผncรผ Yฤฑl Mahallesi 1196 ada 27 ve 31 parsellerde, toplam 60.628 mยฒ alan รผzerinde gerรงekleลtirilen 5 MWe kurulu gรผce sahip arazi tipi Gรผneล Enerjisi Santrali (GES) yatฤฑrฤฑmฤฑmฤฑz tamamlanmฤฑลtฤฑr, santralin Tรผrkiye Elektrik Daฤฤฑtฤฑm A.ล. (TEDAล) nezdindeki kabul iลlemlerini takiben tesis devreye alฤฑnmฤฑลtฤฑr. Sรถz konusu yatฤฑrฤฑm ile ลirketimizin elektrik enerjisi ihtiyacฤฑnฤฑn bir bรถlรผmรผnรผn yenilenebilir enerji kaynaklarฤฑndan karลฤฑlanmasฤฑ, enerji maliyetlerinin azaltฤฑlmasฤฑ ve รถngรถrรผlebilirliฤinin artฤฑrฤฑlmasฤฑ ile operasyonel karbon ayak izimizin azaltฤฑlmasฤฑna katkฤฑ saฤlanmasฤฑ hedeflenmektedir. ฤฐลbu aรงฤฑklamamฤฑzฤฑn ฤฐngilizce รงevirisi ekte yer almakta olup, aรงฤฑklama metinlerinde herhangi bir farklฤฑlฤฑk olmasฤฑ durumunda, Tรผrkรงe aรงฤฑklama esas kabul edilecektir. Our ground-mounted Solar Power Plant (SPP) Project, located in the Yรผzรผncรผ Yฤฑl neighborhood of Yerkรถy, on plots 27 and 31 of block 1196, covering a total area of โโ60,628 mยฒ and featuring an installed capacity of 5 Mwe, has been completed. The facility was commissioned following the formal acceptance procedures conducted by the Turkish Electricity Distribution Corporation (TEDAล). This investment is intended to meet a portion of our company's electricity requirements through renewable energy sources, reduce energy costs, enhance cost predictability, and contribute to the reduction of our operational carbon footprint. The English translation of this disclosure is provided for informational purposes. In the event of any discrepancy between the Turkish and English versions, the Turkish version shall prevail. | |
*** Bu haber, KAP bildirimi esas alฤฑnarak oluลturulmuลtur. Yatฤฑrฤฑm tavsiyesi niteliฤi taลฤฑmaz. Baฤlayฤฑcฤฑ metin aลaฤฤฑdaki orijinal KAP bildirimidir.
Kaleseramik tarafฤฑndan gรถnderilen son KAP bildirimleri
- Kaleseramik elektrik kesintileri nedeniyle Irak’taki รผretimini durdurdu
- Kaleseramik 2026 รผรงรผncรผ รงeyrek sonuรงlarฤฑ ve beklentilerini sundu
- Kaleseramik’in 2026 yฤฑlฤฑ 9 aylฤฑk faaliyet raporu yayฤฑmlandฤฑ
- Kaleseramik’in 1 Ocakโ30 Eylรผl 2026 ana ortaklฤฑk net zararฤฑ 653,6 milyon TL
- Kaleseramik finansal yeniden yapฤฑlandฤฑrma iรงin baลvurdu